Service report format: a free template your engineers can fill in on site
A service report records one service visit: the customer, the machine, the complaint, the work done, the parts used and the customer's signature. Below is a one-page format, a filled-in AC service example, and the mistakes that make a report useless when a customer disputes a visit.
Resonics Technologies · Updated
The service report format
Copy these fields into Word or Excel, or print them on your letterhead. Keep it to one page so the engineer fills in every field instead of skipping half.
| Section | Fields |
|---|---|
| Header | Your company name and logo, report number (e.g. SR-1042), visit date, time in and time out |
| Customer | Customer name, site address, contact person, phone number |
| Equipment | Equipment type, make, model, serial number, installation date, warranty / AMC / chargeable |
| Visit | Visit type (installation, preventive maintenance, breakdown), complaint as reported by the customer, AMC contract number and visit number if it applies |
| Observations | What the engineer found, with readings (voltage, pressure, temperature, error codes) |
| Work done | Each action taken, in order |
| Parts | Part name, part number, quantity, new or replaced under warranty |
| Status | Work completed: yes / no. If no, what is pending and the next visit date |
| Customer feedback | Satisfied: yes / no, customer remarks |
| Sign-off | Engineer name and signature, customer name, phone and signature |
Example: an AC service report, filled in
This is what a preventive maintenance visit on a split AC under an annual maintenance contract looks like with every field filled in.
Report no. SR-1042 · Date 14 August 2026 · Time 11:10 AM to 12:25 PM
Customer Sai Diagnostics, 2nd floor, Shivaji Nagar, Pune · Contact: Mr. Kulkarni, 98xxxxxx21
Equipment 1.5 ton split AC, Daikin FTKF50, serial no. 4K2xxxx819, installed March 2024 · Under AMC
Visit Preventive maintenance, visit 2 of 4 under contract AMC-0042. No complaint reported.
Observations Indoor filter heavily clogged. Outdoor coil dusty. Gas pressure 62 psi. Cooling at grille 14°C.
Work done Cleaned indoor filters and coil with jet pump. Washed outdoor coil. Checked drain line, cleared. Checked electrical connections, tightened loose terminal on outdoor unit.
Parts None.
Status Work completed. Next PM visit due November 2026.
Customer feedback Satisfied. "Cooling better than last week."
Sign-off Engineer: Rahul K. · Customer: R. Kulkarni, signed
What to add for your type of equipment
- Air conditioners and HVAC: gas pressure, cooling at the grille, amp draw on the compressor, whether gas was topped up and by how much.
- Medical and lab equipment: the safety and calibration checks done, software version, and a line for the biomedical engineer's acceptance.
- Water purifiers and RO plants: TDS before and after, filters and membrane changed.
- UPS, inverters and batteries: battery voltage under load, backup time tested.
- CCTV and fire safety: number of cameras or detectors checked, which ones failed.
Five mistakes that make a service report useless later
- "General servicing done" as the work done. A year later nobody knows what was checked. Write each action.
- No serial number. A customer with six ACs can say the one that failed was never serviced, and you can't prove otherwise.
- A signature with no name. Write the name and phone number of the person who signed.
- The report reaches the office a week later. By then a "not satisfied" remark has turned into an angry call to the owner.
- No link to the contract. On an AMC, you need to show that visit 2 of 4 happened, not just that someone came.